How do I change the refresh period on a report in my database?

Related Questions

  • How do I change the refresh period on a report in my database?
  • How can I change the frequency a report is sent out? 

Applies To

  • MyGeotab
  • Reports
  • Configuration
  • Refresh Period

Procedure

To change the refresh period for a report in your MyGeotab database you will do so by the following-

  1. Navigate to Administration
  2. Click Reports
  3. Click Report Views
  4. Select report to update
  5. Select either the Dashboard or Email Report tab
  6. Locate Report Data Configuration
  7. Locate Refresh Period
  8. Select Refresh period desired

Additional Notes

When selecting a refresh period the refresh period options available are the following -

Every 30 Minutes

Every Hour

Daily

Weekly

Every 2 Weeks

Monthly

Every 4 Weeks